Ameren Energy SCR Installation
Coffeen, Illinois
Lift Engineering
Installation of two new Selective Catalyst Reduction (SCR) units
posed major hurdles at this 900MW power plant. Making the tie-in
of the new SCR units in a limited plant shutdown period and under
severe site constraints required an innovative approach to the
demolition of existing ductwork. The project team needed a way
to lift large, heavy preassembled sections (up to 400,000 pounds
and the size of a two-story house). Ruby+Associates developed
an integrated approach to the demolition operations that maximized
use of the existing support structure, expedited the overall project
schedule and minimized disruption of plant operations. The project
was completed within the budget and schedule established by the
owner, entitling the general contractor to the full amount of
the early completion bonus stipulated in the contract. |