Creating a New Motor City Gateway
Interstate 94 Arched Bridge Erection
Bridge Erection Engineering
Wayne County, Michigan
Ruby+Associates performed construction engineering for these twin
tied-arch bridges-each supporting a 240-ft-long deck span designed
to carry four lanes of traffic. The design and erection had to
minimize disruptions to traffic and meet a deadline that could
not be extended. Ruby proposed an alternate construction method
that eliminated the need for massive and expensive shoring.
Challenges:
 |
As originally designed, temporary shoring
towers were to support not only the bridge deck steel,
but also the formwork, rebar, screed machines and deck
concrete. The towers would have had to support 120,000
pounds while maintaining an installation tolerance of
plus-or-minus 1/8 inch for the deck elevation.
The available window below the deck steel
for the spandrel system over heavily traveled Telegraph
Road was approximately 30 inches. Creating a spandrel
system that was stiff enough to resist 240,000 lb of vertical
load over the road while limiting the deflection to 1/8
inches was not cost effective.
The complex geometry of the arch sections
required specially designed hitch fixtures to securely
grasp the sections and also tilt the pieces inward once
in place. This was complicated by strict design requirements
that did not allow any penetrations or welds to the arches. |
 |
Solutions:
 |
An alternate plan reduced the weight
on each shore to just 32,000 lb and minimized tight tolerances
during installation: only the bridge steel was supported
by the shoring towers while the remaining bulk of the
span's weight was shifted to the bridge's arches through
the tensioning of the cable strands.
By using the arch to support the dead
load during construction, crews used a less expensive,
rented shoring system instead of larger, specially fabricated
shoring towers.
The smaller shores required only timber
mats at the base. Because they were easily removed once
the load was transferred, they could be immediately reused
for construction of the second bridge. Additionally, the
impact on Telegraph Road was minimized.
Three hitches were designed to lift the
sections and to rotate the arch. These never directly
touched the steel. Half-inch strips of polyurethane material
were placed between the hitches and the arch sections
to provide padding and friction resistance so that no
bolts or welds were required to be attached to the arch
segments. |
 |